Stage payments explained: how to protect your money until handover

How do you pay without money running ahead of the work, and without the contractor stalling for cash? The advance and its guarantee, a payment per stage, retentions and variations.

Reading time: 2 minutes Reviewed by Al Noor's engineering team

Two workers tying the rebar of a raft foundation
Two workers tying the rebar of a raft foundation

The biggest worry of anyone building a home is money: how to pay without the money running ahead of the work, and without the contractor stalling for lack of cash? The answer is a payment schedule tied to finished stages approved by the consultant, not to dates on a calendar.

The advance and its guarantee

An advance of 10 to 20% is usually paid on signing so the contractor can set up the site and order materials. Protect it with a bank guarantee issued by the contractor for the same amount, reduced step by step with the later payments.

A payment for every finished stage

Here is an example from our payment schedule for a G+1 villa:

Stage Payment Paid so far
Advance on signing (against a bank guarantee) 10% 10%
Excavation and foundations 15% 25%
Concrete frame 25% 50%
Blockwork and plaster 15% 65%
MEP works 10% 75%
Finishes and facades 15% 90%
Inspection, handover and completion certificate 10% 100%

No payment falls due until the consultant has visited the site and approved the stage in writing.

The steel frame of a warehouse under construction, with block walls
Every stage is approved before it is paid

Retention: the last line of defence

Many contracts hold back 5 to 10% of each payment; half is usually released at handover and the rest after the maintenance period. That makes sure the contractor comes back to fix anything that appears after you move in.

Variations

  • Any change in design or materials goes into a variation order with its price and time before it is carried out.
  • Do not pay for additional works you have not signed for.
  • Ask for an updated statement of the total value after each variation.

Before every payment, ask:

  1. Has the consultant approved the stage in writing?
  2. Does the work match the bill of quantities and the specification?
  3. Have the retention and the advance recovery been deducted as the contract says?

This is general information for awareness, and contract terms differ between projects; review your contract with your consultant or legal adviser before signing.

Note: This guide is general information for awareness, and rules and fees may change. Always check with your registered consultant and the competent authority before any decision.