The biggest worry of anyone building a home is money: how to pay without the money running ahead of the work, and without the contractor stalling for lack of cash? The answer is a payment schedule tied to finished stages approved by the consultant, not to dates on a calendar.
The advance and its guarantee
An advance of 10 to 20% is usually paid on signing so the contractor can set up the site and order materials. Protect it with a bank guarantee issued by the contractor for the same amount, reduced step by step with the later payments.
A payment for every finished stage
Here is an example from our payment schedule for a G+1 villa:
| Stage | Payment | Paid so far |
|---|---|---|
| Advance on signing (against a bank guarantee) | 10% | 10% |
| Excavation and foundations | 15% | 25% |
| Concrete frame | 25% | 50% |
| Blockwork and plaster | 15% | 65% |
| MEP works | 10% | 75% |
| Finishes and facades | 15% | 90% |
| Inspection, handover and completion certificate | 10% | 100% |
No payment falls due until the consultant has visited the site and approved the stage in writing.

Retention: the last line of defence
Many contracts hold back 5 to 10% of each payment; half is usually released at handover and the rest after the maintenance period. That makes sure the contractor comes back to fix anything that appears after you move in.
Variations
- Any change in design or materials goes into a variation order with its price and time before it is carried out.
- Do not pay for additional works you have not signed for.
- Ask for an updated statement of the total value after each variation.
Before every payment, ask:
- Has the consultant approved the stage in writing?
- Does the work match the bill of quantities and the specification?
- Have the retention and the advance recovery been deducted as the contract says?
This is general information for awareness, and contract terms differ between projects; review your contract with your consultant or legal adviser before signing.